Countryside Water Main and Road Improvements

Update:


 
Overview:





Start:

End:

Agency:

Cost:

Impacts:




Contact:


Documents:
Project work is substantially complete.
 
The project involves the replacement of over 15,000 feet of 8 and 12 inch water main and the resurfacing of the streets within the Countryside subdivision. The water main work and installation of the binder course pavement was completed in 2016.The final lift of asphalt (surface course) will be installed in the spring of 2017.

Impacts to traffic are expected to be minimal; however daytime lane and roadway closures should be expected.

Mid-April 2016

Summer 2017

United City of Yorkville

$4,900,000 (Construction Only)

Typical to projects of this nature, residents may experience the following during construction:
  • Construction noise and traffic
  • Minor traffic delays
  • Temporary driveway closures
Kyle Welte, P.E - Resident Engineer (EEI)
630-774-1943, kwelte@eeiweb.com

Full Project Map